Delayed Ferguson Marine ferries may not be completed until 2023

The Glen Sannox ferry is not now due to be completed until at least April 2022. Picture: Mark Gibson.The Glen Sannox ferry is not now due to be completed until at least April 2022. Picture: Mark Gibson.
The Glen Sannox ferry is not now due to be completed until at least April 2022. Picture: Mark Gibson.
Glen Sannox and unnamed second CalMac vessel will be delivered at least four years late

Two ferries due to be in service in 2018 have been delayed further by coronavirus and will not be ready until 2022 and 2023, economy secretary Fiona Hyslop revealed to MSPs today.

The Ferguson Marine shipyard in Port Glasgow was awarded a £97 million contract to build the vessels, designated 801 and 802, before it collapsed into administration last August and was saved by the Scottish Government.